Project Background/Description

The Department of Parks and Recreation is replacing the Summerfield Park playground equipment at 8550 Chatsfield Way, North Englewood, MD. The playground replacement involves the removal and disposal of the existing equipment that has exceeded its useful life and the installation of new play equipment for both 2-5 and 5-12 age groups. To make the playground more accessible for park users, the playground will also be relocated closer to the Chatsfield Way parking lot and will be over 7,000sqft in size.

Status/Project Updates

Last Updated February 2022

Currently, the project is in the Design phase. A summary of anticipated milestones is as follows:

  • Winter 2022 – Community Engagement
  • Spring 2022 – Design
  • Summer 2022 – Construction Documents/Permits
  • Winter 2022 – Construction

Actual dates for the completion of the milestones are subject to change.