The Construction Documents Phase of the Tucker Road Ice Rink replacement project has been completed. In February, the design team, Grimm + Parker, conducted a series of meetings with DPR operations and maintenance staff to finalize the design.
The next phase has begun. During this phase, DPR will complete negotiations of the Guaranteed Maximum Price (GMP) with Forrester Construction, our construction manager.
Anticipated milestones and activities as developed by Forrester Construction include:
- Spring 2019 – Guaranteed Maximum Price negotiation completed
- Spring 2019 – Site Permits released and Building Permit Submission expected
- Spring 2019 – Construction Begins for site-work
- Fall 2020 – Completion of on-site construction activities
Actual dates for the completion of the milestones are subject to change.
The current projected schedule reflects the additional time that was required to complete the initial procurement process, and the time associated with securing supplemental funding during the FY19 budget process. The anticipated project completion is Fall of 2020. Forrester Construction will continue to refine the project schedule based on work progress and other factors that influence the project delivery. Upcoming communications will include an announcement about the demolition event for the existing facility.